Project Update - Barton Court Grammar School

Barton Court Grammar School is progressing well with the completion of substructure brick & block work, internal block work partitions and the first floor screeding. Additionally the first floor partitions have now commenced on site and the construction to the roof light is nearly complete.

The scheme is due to be waterlight by September.

Betteridge & Milsom are working alongside Jenner Contractors.